Citation: ORS 183.430
Section: 183.430
183.430, 183.440 to 183.460 and 183.470. After such hearing, the director shall enter an order containing findings of fact and conclusions of law. The order shall rescind, affirm or modify the director�s initial order. Appeals from the director�s final order may be taken to the Court of Appeals in the manner provided by ORS 183.482.
����� (8) Except for a permit issued under the process set forth in ORS 517.952 to 517.989, the director shall:
����� (a) Determine whether an application is complete within 30 days from the date the Department of State Lands receives the application. If the director determines that an application is complete, the director shall distribute the application for comment pursuant to subsection (5) of this section. If the director determines that the application is not complete, the director shall notify the applicant in writing that the application is deficient and explain, in the same notice, the deficiencies.
����� (b) Issue a permit decision within 90 days after the date the director determines that the application is complete unless:
����� (A) An extension of time is granted under subsection (10)(b) of this section;
����� (B) The applicant and the director agree to a longer time period; or
����� (C) The director determines that an extension is necessary to coordinate the issuance of a proprietary authorization decision for an ocean renewable energy facility under ORS 274.873 and a removal or fill permit decision.
����� (9) Permits issued under this section shall be in lieu of any permit or authorization that might be required for the same operation under ORS 164.775, 164.785, 468.020,